AbitareIn has launched a partial tender offer at 3.10 euro per share and on 17 December will ask shareholders to wind the company up, while two of the projects sold to Techbau are coming back. Days later Milan prosecutors asked to drop the best-known strand of the planning probe. Read together, the two events show what waiting costs a developer.

On 6 November AbitareIn's board took two decisions. The first is a partial tender offer for its own shares: 2,580,645 shares, 9.7% of the capital, at 3.10 euro each, for a maximum outlay of 7,999,999.50 euro. The second is an extraordinary general meeting on 17 December to vote on early dissolution and voluntary liquidation.

According to the company's announcement, the offer runs from 9 to 27 November. The amount is technical: below 8 million the offer stays under the threshold and the document does not need Consob approval, although AbitareIn chose to publish the information anyway. The price carries a 12.33% premium on the official 5 November price and, on 26.6 million shares, values the whole company at about 82.5 million euro.

On 10 November Milan prosecutors asked to drop the case against sixteen suspects in the best-known strand of the city's planning investigation.

A company that lost its cycle

AbitareIn was built around one cycle: buy disused sites in Milan, obtain the permit, build, sell flats. Its subsidiary Homizy works in co-living for rent, but the core of the group was always development for sale. That works as long as the time to construction is predictable.

The freeze on planning procedures made that time open-ended. At the end of July the group sold Techbau 14 vehicle companies, each holding a residential project awaiting permits, at an enterprise value of 141.1 million, cutting consolidated debt by an estimated 135 million. The exit was not complete. On 30 October, as Teleborsa reported, Techbau exercised a put option on two of those companies: AbitareIn will buy them back for 12.1 million, offset against the third price instalment due by September 2027. Two sites without permits are coming back to a company about to ask shareholders to wind it up.

The board cites the lack of new projects within certain and reasonable timeframes. Boilerplate, perhaps, but it captures the economics of building for sale: a site without a permit earns nothing and no rent pays for the wait. Every month brings interest, overheads and, on pre-sold projects, buyers waiting for their keys.

Who can afford to wait

The sale to Techbau shows who can hold a frozen Milan site today. A builder earns on the building work as well as on the sale, and its horizon and cost of waiting differ from those of a listed company reporting to shareholders every six months. At equal theoretical value, the same sites are worth more to whoever bears delay better. The market moved them there. Not all of them, as the put shows.

The offer price and the liquidation value

Minority shareholders face a choice between two uncertainties. In August, according to Milano Finanza, AbitareIn itself had minuted a theoretical post-sale value of around 4 euro per share, based only on the cash generated, and some minority investors were working with a 3.9 to 4.3 euro range. That estimate predates the Techbau put, which removes 12.1 million from the expected proceeds and brings back two projects whose realisable value is still unknown.

The company warns that the offer price is not an estimate of what liquidation might distribute and that it cannot yet say which route is better. Realisation values, liabilities including contingent ones, and the cost and length of the process will all count. None of them can be pinned to a number today.

Founders and main shareholders Marco Grillo and Luigi Gozzini have said they will not tender. That allows several readings, from confidence in the liquidation value to a long-term commitment.

Dropping charges does not restart building sites

The prosecutors' request makes the case more instructive. Their note, reported by Domani, says there is no proof of a corrupt agreement strong enough to predict a conviction, and Avvenire points out that prosecutors fell in line with earlier rulings by the review court and the Court of Cassation. A preliminary judge must now decide, and other strands remain open. Even if the request is granted, no site will restart because of it.

Stalled permits depend on the city's choices on procedure, from simple notices to full implementation plans. The Comitato Famiglie Sospese, which groups buyers still waiting for their homes, reacted at once: as Avvenire reported, for those families the nightmare goes on.

Administrative risk hits capital long before a judge or a new rule closes it. Here it moved land towards those who could wait and pushed into liquidation a company whose model relied on short waits. In valuing a Milan site today, what can be built matters, and almost as much, who will have the strength to reach the permit.